TIMELINE

PROJECT MILESTONES

MARCH 2023

Land purchase offer and beginning of due diligence

Purchase offer

DECEMBER 2023

Land acquisition and CCU approval for development project.

CITY APPROVAL FOR PROJECT

FEBRUARY 2024

Issuance of construction permit and demolition of existing building on site

CONSTRUCTION PERMIT

MARCH 2024

Beginning of land excavation and a timeline of 12 months for the construction of the project.

start of construction

JANUARY 2025

Completion of the construction phase of the project

completion